6 March 
2025

UPDATE ON ACORN ANAEROBIC DIGESTER APPLICATION

Following the February update, much less to report this month. 

The updated community response was submitted to the council in line with the consultation deadline on 7th February. It can be viewed on the Bucks CC planning portal – linked from saynotoacorn.co.uk. In the past couple of days, Acorn have uploaded a number of new documents, in response to our latest objection. None of these Acorn documents change anything with regards to our objections: their industrial scale plant is still entirely inappropriate in terms of its scale and location. 

The team has been keeping in close contact with Bucks CC to check when the application will be considered by the Strategic Sites Committee. Unfortunately, we remain in a groundhog day situation regarding the meeting date: it’s now looking increasingly likely that the application will not be considered before the council elections on 1st May. The additional Strategic Sites committee meeting that the council arranged in February was cancelled almost as soon as it was arranged, and whilst there is still scheduled to be a meeting on Friday 14th March, our understanding is that the Acorn application will not be considered at it. Six weeks of purdah follows this, and we will then wait for the new council to be formed – and strategic sites committee members to be nominated. 

All we can do for now is continue to watch and wait. 

UPDATE ON ACORN ANAEROBIC DIGESTER APPLICATION

5 February 2025

What’s happened? 

Since the update in the January Crier, a lot continues to go on: 

  • The closing date for the public consultation was pushed back to Friday 7 February 
  • We received confirmation that the application would not be considered at the February Bucks CC Strategic Sites Committee meeting on 13th February. An additional Emergency Strategic Sites Committee meeting has now been scheduled for 24th February (morning), to ensure the council get through the backlog prior to the May elections. We hope that the Acorn application will be considered either at this meeting or the 13th March meeting. Greg Smith MP is also helping to push this forward. 
  • A traffic report was commissioned jointly by Parish Councils of Oakley, Chearsley, Chilton, Worminghall and Shabbington to respond to the latest data that Acorn included in their submission in December 2024. (Long Crendon Parish Council was also invited to share the cost of commissioning the report). This report has been submitted to the Highways Officer ahead of the 7th February deadline.   
  • Going alongside the traffic report above, an updated community response is being submitted to the council, including responses on key planning consideration of landscape character and a comprehensive (80 page) analysis and photo database of all the Acorn traffic receptor sites mentioned in their submission. 
  • Acorn meanwhile has been running a totally misleading campaign across social media, simply stating: “we need your support, to help our local farmers”. Once respondents click through they are provided with some total greenwash statements about the proposal and when people fill in a single question survey, these comments are fed directly through to the Bucks CC planning portal as ‘supporting’ comments. Almost all of the comments make totally irrelevant points, unrelated to the development. The PR company running the campaign is led by a Bucks councillor – both the campaign and this relationship has been reported to the council. 
  • The Say No to Acorn group – helped by a very active new team of communications experts – have been running our own social media campaign. These activities, together with posts from Greg Smith MP, have helped to boost the number of signatories to the community objection to over 1600. It’s not too late to become a signatory if you haven’t done so already – go to www.saynotoacorn.co.uk and click the link to sign the community objection. 
  • In addition to individual and community objection signatories, all local Parish Councils have also submitted objections to the development: Oakley, Brill, Chearsley, Chilton, Cuddington, Long Crendon, Shabbington, Worminghall. 

Keep an eye out for news of the 24th February or 13th March Strategic Sites Committee meetings – we will communicate through Facebook and other informal local channels. We would appreciate as many people as possible to come to the meeting, to show the committee on the day the strength of feeling locally. By the time of the March Crier, we may have a decision, or be close to getting one. And needless to say, let’s hope that the Strategic Site Committee members realise what a totally destructive scheme this is, for local people, our villages and the environment and say NO to Acorn. 

January 2025

Our fight is reported on BBC News South - 12/1/2025

Thank you to many of you who have been trying to object on the Bucks CC website. Unfortunately as people have experienced, the site seems to have been 'down' more than it's been working for the past few weeks. We keep letting them know, and thank you to others who have also done the same.

We have now heard that the February Strategic Sites Committee meeting has also been cancelled, so the application will not be considered in February. This means that - as a minimum - objections can be received until 7 February, but we expect that deadline to be extended further.

As per our update in the Crendon Crier and online, the Say No To Acorn group are working on the addendum to the original community objection - responding to Acorn's re-submission in December. The extended deadline means we have a bit more time to do this, but we are aiming to send it round to the community for signature hopefully by the end of January.

Some of you will have seen the feature on BBC South on Sunday 12th January 2025. Whilst of course these features are always shorter than you'd want them to be, hopefully it helped to raise awareness and was a good opportunity to link up with Greg Smith MP. Thanks to Ros Finney Paul Newell and Jo Grey for being involved with this. 

UPDATE ON ACORN ANAEROBIC DIGESTER APPLICATION 

1 January 2025

What’s happened?

Acorn have added more documents to their application and Bucks Council have written to people who had commented, inviting further comments, and giving a new deadline of 18th January. Given this deadline, the application could be considered at the Buckinghamshire County Counci Strategic Sites Committee meeting scheduled for 13 February 2025, although this has not been confirmed.

What are the updates in the application?

Acorn claims to have made a number of concessions to address objections and concerns raised by residents. However, it is important to note that none of the changes are legally enforceable, nor are they supported by existing planning permissions; they are statements of intent.

The main changes included in Acorn’s new documents are:

1. The site has been extended to allow direct injection to the gas grid. This provides some validity to the site location. However, alternative (potentially more suitable) sites still don’t appear to be considered. It is also not clear when or how much gas will actually end up being injected directly to the gas grid as Acorn are still protecting the rights for Biogas export by road, nor is it confirmed whether Acorn has any agreement to access the gas network. Furthermore, Acorn does not appear to have accounted for the energy and CO2 emissions that would be required to clean and compress biomethane prior to injection into the gas network (these could be significant).

2. The new track to gas injection point is also used to deliver feed via an extensive network of farm tracks; (as yet unidentified), apparently relieving the highway. The suggested reduction is 10% or 1192 two-way yearly movements. The track from Worminghall off the highway will not be used, and it is not confirmed whether Acorn has the requisite permissions to use farm tracks instead of the highway.

3. Generally Acorn claim their revised proposals reduce traffic volume by 28% which will require careful analysis. They further offer S106 obligations capping the peak daily number of two-way HGV trips at 140 per day (ie 70 into the site and 70 out of the site, relative to the 94 per day included in their original submission) and limiting the hours of permitted movement. Whilst Acorn has offered these as conditions of planning permission, there is no clear consequence of failure to meet this cap.

4. There is the continued reference to the fact that none of the technical consultees have raised objections. To our knowledge, technical consultees have not been reconsulted since the community objection was submitted.

What information is still missing in the application?

There is still no information included regarding the whole life carbon impacts of the Acorn industrial development. During the construction phase alone, considering solely the concrete required to construct the site (estimated to be over 230,000 Tonnes) the CO2 emissions would be equivalent to 6 months of CO2 emissions for the whole of Aylesbury. The overall impacts of the project, including impacts on food production by switching crops to feed the Acorn plant, have not been provided.

What are the Say No to Acorn Group doing in response to the latest Acorn application?

For the initial formal community response, the group commissioned a traffic report and visual impact study, thanks to funds raised from the community through GoFundMe. An updated visual impact study (currently in progress) will show the impact of the AD plant on the local landscape during winter months. In addition, a further report from traffic experts is being commissioned to scrutinise and respond to Acorn’s latest traffic data. Information from these two reports, plus any additional responses, will be submitted to Bucks CC ahead of the 18 th January deadline as an addendum to the full community response.

What do you need to do? 

1. If you haven’t already made an objection, please do so through the Bucks CC planning consultation portal prior to the 18th January deadline (you can find the link and guidance on www.saynotoacorn.co.uk.)

2. If you have already submitted an objection, you can add an additional comment to reiterate your continued opposition to the proposal. Simply log in to the website, and it will automatically connect this with your previous comment.

Exactly what you write depends on what you included previously, but you can use the bullet points above as a guide (please do use your own words). We do not consider that any of the updates that Acorn have made to their application makes their development any less harmful to the environment and our communities. 

3. Add your signature to the updated community response. Once we have updated the formal community response - with information from the new reports commissioned above - we will notify those registered by email and also through the SayNoToAcorn Facebook group. Or you can add your signature directly via the link on www.saynotoacorn.co.uk .

Please keep an eye on emails and the SayNoToAcorn group on Facebook for further information as we receive it. It is no coincidence that Acorn chose to submit their updated application so close to Christmas, when they judged that members of the community would be distracted by holidays and have less time to regroup and respond. Given the short timescale, we would appreciate your help both in adding to your own objections and spreading the word to friends and neighbours.

December 2024

Urgent Action is Needed

Acorn has submitted additional documents for their application, prompting Buckinghamshire Council to invite further public comments with a new deadline of 18th January 2025. While unconfirmed, it is likely the application will be reviewed at the Strategic Sites Committee meeting on 13th February 2025.

  • Download and read the document below
  • Submit your objection here
  • IMPORTANT if you previously objected please register a new comment here (which will add to your old objection) to address Acorn's revisions, reaffirming your opposition and emphasising that the changes do not reduce the development's environmental or community impact
  • Sign the community objection below

December 2024

We urge you to be a signatory of the community objection to the Hornage Anaerobic Digester application

Our initial community response was submitted to Bucks CC on 22nd August 2024 (you can download this here c2ace24a-20ee-4a33-9a2b-320c1b6fe5cb)

In response to Acorn's new submissions on 19th December 2024, an updated visual impact study has been commissioned to show the impact of the AD plant on the local landscape during winter months. In addition, a further report from traffic experts is being commissioned to scrutinise and respond to Acorn’s latest data. Information from these two reports, plus any additional responses, will be submitted to Bucks CC ahead of the 18th January deadline.

To sign the community objection please complete this link:

We need your consent to load the translations

We use a third-party service to translate the website content that may collect data about your activity. Please review the details in the privacy policy and accept the service to view the translations.